KALISTE SALOOM WIDENING PROJECT UPDATE

Apr 6, 2022, 08:41 AM by Jennifer McCommons

LCG-Logo-298x123

KALISTE SALOOM WIDENING PROJECT UPDATE

Lafayette, LA – The Kaliste Saloom Road Widening Project is expected to be complete in August 2022, weather permitting. Contractors are currently ahead of the original contracted completion date of September 2022. 

Workers are currently installing yard drains, completing catch basin and manhole tops, installing street lighting, constructing concrete curbing, sidewalks, and driveways. They will proceed southward from Farrel Drive. Once those tasks are complete, contractors will begin striping and signing the roadways.

When complete, the 2.2-mile stretch of Kaliste Saloom to E. Broussard Road will have five lanes, a turn lane in the middle and sidewalks.